- Home
- Government
- Departments
- Communications & Public Engagement
- Marketing and Communications
- Stadium Streets Project
Stadium Streets Project
The Stadium Streets Project:
As the City of High Point prepares for new downtown development, portions of N. Elm Street, Lindsay Street, Pine Street and English Road will receive underground utility improvements.
Appling Way Updates:
This Week – 5/27 to 6/3
- Finished installing Water Line on Virginia and tested
- Fiinishing up the Duct Bank on Appling Way
Next Week – 6/3 to 6/10 - finish Chlorination of water line Virginia Place
- Begin installing sewer on Virginia
- Finish working on Appling Way Duct Bank and demobilize
- PNG/SEC mobilize and begin installing gas line on Appling
This Week – 6/10 to 6/17
- Finished water line and tied in
- Began working on Virginia Sewer. Approximately 2 more weeks
- Mobilized to Appling to begin grading. Rain is holding us off
Next Week – 6/17 to 6/24
- Continue sewer Virginia Place
- Continue/begin grading on Appling Way
This Week – 6/17 to 6/24
- Worked on Sewer in Virginia Place
- Worked on Grading Appling Way
Next Week – 6/24 to 7/3
- Continue/Finish sewer Virginia Place
- Begin added storm sewer section on Appling Way
- Continue Grading Appling Way
This Week – 7/1 to 7/8
- Finished grading Appling Way
- Began installing asphalt on Appling Way
- Working on 24 inch Storm Sewer behind Plant 7
Next Week – 7/8 to 7/15
- Finish the 24 inch storm sewer behind Plant 7
- Continue working on Asphalt paving Appling way
This Week – 7/22 to 7/29
- Worked on Curb and asphalt on Appling Way
- Staked for retaining wall
- Finished Virginia Place
Next Week – 7/29 to 8/5
- Continue curb and asphalt on Appling Way
- Start building the retaining wall
- Begin demo of Pine Street (Pine Street Elevations Needed)
This Week – 7/29 to 8/5
- Started Demo of Pine Street
- Completed Retaining Wall Minus the associated fencing
- Pike, Northstate and Spectrum began adjusting their vaults to finished elevation
- Virginia Place completed and street reopened
- Formed for curb behind Plant 7
Next Week – 8/5 to 8/12
- Pour Curb behind Plant 7
- Continue grading sidewalk on Appling Way
This Week – 8/12 to 8/19
- Started installing sidewalk along Appling Way
- Started/continued demo of Pine Street
Next Week – 8/19 to 8/26
- Continue Sidewalk on Appling Way
- Continue Demo of Pine Street
This Week – 8/19 to 8/26
- Installed curb behind Plant 7
- Installed drainage swale adjacent to the retaining wall
- Continued demo of Pine Street
Next Week – 8/26 to 9/2Done Editing
- Continue demo of Pine Street
- Continue sidewalk on Appling Way
- Continue paving
This Week – 8/26 to 9/2
- Continued demo of Pine Street
- Continued sidewalk on Appling Way
- Installed Fence at retaining wall
- Continued curb on Appling Way around curve tying into Pine
- Installed Asphalt around curve on Appling way tying into Pine
Next Week – 9/2 to 9/9
- Continue demo of Pine Street
- Continue sidewalk on Appling Way
- Continue paving
This Week – 9/9 to 9/16
- Installed base asphalt on Pine Street
- Installed curb on Pine Street
- Installed sidewalk on Appling Way
- Installed Trench drain on Appling Way
Next Week – 9/16 to 9/23
- Grade out for sidewalk on Pine Street
- Install intermediate and 1.5” of surface asphalt on Pine Street